Apr-May 2022: Community Consultation
Community consultation was held to hear feedback from local businesses and residents.
Jul-Aug 2022: Concept Design Finalised
Following the consultation period, feedback was consolidated and the concept design was finalised.
Sep 2022 – Jun 2025: Creation of detailed designs
The design contract was awarded to Group GSA and has since undergone several rounds of revisions. The detailed design has now been finalised.
Jun 2022 – Sep 2025: Procurement
Suitably qualified contractors will be sought to deliver the works.
Nov 2025 – Mid 2026: Construction
Construction is expected to commence in late-2025 with completion by mid-2026.
The project is split into three stages with shops expected to remain open during construction.
There may be some disruption to vehicle traffic during each stage.
Stage 1 - Eastern Laneway and Upper Car Park
Upper car park will be closed with access closed from Bank Place. Through vehicle traffic on Commercial Place to continue via Young Street service road. Pedestrian access available to all shops.
Stage 2 – Festival Lane and Commercial Place
Through vehicle traffic on Commercial Place will be closed. Festival Lane will be closed. Pedestrian access available to all shops.
Stage 3 – Western Laneway and Commercial Place
Through vehicle traffic on Commercial Place will be closed. Western laneway will be closed. Pedestrian access available to all shops.
*Timelines are subject to change.