Apr - May 2022: Community Consultation
Community consultation was held to hear feedback from local businesses and residents.
Jul - Aug 2022: Concept Design Finalised
Following the consultation period, feedback will be consolidated and the concept design was finalised.
Sept 2022 - Jun 2025: Creation of Detailed Designs
The design contract was awarded to Group GSA and has since undergone several rounds of revisions. The detailed design has now been finalised.
Jun 2025 - Sept 2025: Procurement
Suitably qualified contractors will be sought to deliver the works.
Nov 2025 - Apr 2026: Construction
Construction.
Mar 2026 - Jun 2026: Public Art
Expressions of interest will be sought from qualified artists to explore public art opportunities in the revitalised laneways.
*Timelines are subject to change.