Rollo Street Park Redevelopment

  • Project typeRedevelopment
  • Project value$1.77 million
  • Project scheduleExpected completion in December 2025
  • Contractor nameSustainable Landscaping Pty Ltd
Rollo Street Park

Rollo Street Park is undergoing a $1.77 million redevelopment, following a strong desire from the local community for this area to be repurposed. 

The project will see the vacant land of the old Yarragon Primary School transformed into a valuable community open space that accommodates passive recreation and community events.

Key features of the upgrades will include: 

  • The planting of more than 60 trees 
  • The resealing of Hanns Lane with diagonal parking
  • A walking path
  • Seating
  • A drinking fountain
  • Bike racks
  • Rain gardens
  • Improved drainage
  • New bollards and fencing
  • Shelter
  • Signage
  • Artwork.

Background

The site at 3-5 Rollo Street, Yarragon was the original location of the Yarragon Primary School from 1879 to 2013. In 2019, Council resolved to purchase the site to retain it as a community asset for use as public open space.

Through a master plan completed in 2021 and further input from a project reference group (PRG) in Yarragon, the park redevelopment works will include the planting of 63 new trees, the sealing of Hanns Lane with diagonal parking, a loop walking path, seating, a drinking fountain, bike racks, rain gardens, and fencing.

Following a competitive tender process, Sustainable Landscaping Pty Ltd was successful in securing the contract and commenced works on-site in November 2024.

The second stage of works includes shelter, signage, and artwork.

Project funding

This $1.77 million dollar project will be jointly funded by Council and the Victorian Government through its Growing Suburbs Fund.

$235,500      Council

$1,529,000    Victorian Government

Project updates

December 2024

The contractor commenced on-site in November and started with the demolition of the old chain mesh fencing. Hanns Lane and the area for new angle parking was excavated in late November but due to a period of wet weather, works were temporarily slowed down.

As weather conditions improved, the gravel road base for the laneway and car parking area could be imported and compacted. Other works that have been completed include the installation of a new water meter for garden maintenance and the drinking fountain, a stormwater drainage pipe within Hanns Lane, and earthworks for the new loop path.

Hanns Lane will be temporarily reopened to residents only during the Christmas period. Sustainable Landscaping will return to site on 13 January 2025 to resume works. 

February 2025

Sustainable Landscaping re-commenced work in January 2025. As of February 2025, garden beds have been excavated and are being prepared, concrete has been completed for new parking bays in Hanns Lane, concreting is in progress for the park’s loop footpath, and preparations are being made for the Hanns Lane asphalt traffic lane.

May 2025

The centre grass area has been levelled and hydroseeded, park furniture has been installed, the Hanns Lane crossovers have been completed, asphalt has been laid in the laneway, and the fencing, bollards, and edge strip have been installed. All that remains for Stage 1 is for the turf and planting to establish. Preliminary Stage 2 work is underway, including the design of a new shelter, the engagement of an artist for an interactive artwork, and the finalisation of signage design.

October 2025

Stage 1, which included landscaping, Hanns Lane car park and sealing, footpath, and drainage, is now complete.

Stage 2 works, which include the shelter, signage, and artwork are currently underway.

  • The bronze sculpture art pieces are currently being manufactured and are expected to be completed by early November. They will be installed on some large granite boulders which have already been placed on-site.
  • A builder has been engaged and construction of the shelter is expected to commence late October/early November and be completed in December. Various signage will also be installed around the park.

Temporary fencing is currently in place around the whole park. Following completion of the artwork, temporary fencing will be adjusted to allow wider access where required.

Timeframe

Estimated project works timeline:

Date 

Task 

Status 

September 2024 Award tender  Complete
November 2024 Contractor establishment on-site  Complete
November 2024 Demolition works Complete
November 2024 Excavation for Hanns Lane and car park  Complete
December 2024 Stormwater pipe construction Complete 
December 2024 Hanns Lane and car park sub-base  Complete
December 2024 New water connection Complete
December 2024 Hanns Land and car park base Complete 
December 2024 / January 2025  Loop path earthworks Complete 
February 2025 Concrete edging and kerbs Complete
February 2025 Hanns Lane concrete car park Complete
February 2025 Concrete loop path Complete
February 2025  Topsoil for garden beds and grass areas Complete
March 2025  Hanns Lane asphalting Complete
March 2025  Hydroseeding new grass areas Complete
March 2025 Installation of park furniture, fencing, and bollards Complete
March 2025 Garden bed mulching and planting Complete
From April 2025 Grass establishment Complete
December 2025 Completion of future works outside of current construction contract (shelter, signage, and artwork) On Track


The above dates are estimated only and subject to change. The timeframe will be updated as the project progresses.

Contact us

Have questions? We are here to help!

For more information, please contact Council's Major Projects on 1300 229 229 or email projects@bawbawshire.vic.gov.au