Project  Scope  2017-18 Adopted Budget  Estimated Completion  Status 
Recreation Design Works Design works for priority recreation projects $213,211 May 2018 On Track
Brooker Park Renew BBQ and Picnic shelter including connections $69,294 Feb 2018 On Track
Open space design Design key existing and new open spaces to meet OS guidelines $10,661 May 2018 On Track
Parks and Open Space Improvements Annual Program (responsive works) $41,027 May 2018 On Track
Annual Playground Equipment renewal, and upgrade Program Renewal of ageing equipment- responsive works $58,633 May 2018 Completed