Recreation Facilities Projects

Project   Scope 2017-18 Adopted Budget  Estimated Completion  Current Status
Buln Buln Recreation Increase run off of netball court (tennis side) and relocate fence $64,976 Mar 2018 On Track
Buln Buln Recreation Realign western tennis court closer to eastern court and remove internal fence $14,712 Mar 2018 On Track
Bellbird Park Western Section Future expansion of cricket net facilities $117,825 Dec 2017 On Track
Drouin Recreation Reserve Recommission cricket nets  $35,180 Nov 2017  On Track
Half basketball Court, Noojee Construct new half basketball court $40,000  Feb 2018 On Track
Sports Court Renewal Program Annual Program- responsive works $65,028 May 2018 On Track
Sports Field Rehabilitation Responsive works- includes oval renewal, drainage & irrigation works
$106,606  May 2018 On Track
Western Park Recreation Precinct

Develop new senior sports field including floodlighting for training purposes on western side of Tarwin St. (on-going from 16-17)

$1,082,142 Apr 2018  On Track
Athlone Reserve Ground renewal $24,519 Jan 2018 On Track
Hallora Recreation Reserve  Installation of an additional water tank  $12,260 Jan 2018  On Track
Jindivick Recreation Reserve Make safe bank where stairs used to be and the ground has fallen away  $98,077  Jan 2018  On Track
Jindivick Recreation Reserve Make safe area where the path is falling away on the ramp down to the cricket nets  $24,519  Jan 2018  On Track
Neerim South Reserve Address erosion issues on embankment  $73,558 Jan 2018  On Track  
Ellinbank Reserve New light poles and light upgrade for oval  $180,164  Feb 2018 On Track  
Recreation Lighting Renewal Program Renewal of lights at various locations- responsive works  $46,352  May 2018  On Track